The project is now four days old and the team has gone almost two blocks east of the City Building down Patterson Street, laying in 6-inch pipe.   This is one of the worst stretches of pipe in the community, having been patched any number of times in the past.  

The team is happy with their effort and are beginning to better understand their respective roles. 


This picture looks north down Howe Street.  Pipe can be seen laying on the ground in preparation for the coming trench. 

The line is 42-inches deep. 

Eight-inch pipe has also been laid out to the tower.  Plans are to link up the tower as quickly as possible once the line has been laid along Patterson Street between Main and Omio Streets.  Most think this will happen next week.   

Table of Contents

Next Day


If you have support or general questions please email us at: support@nckcn.com
If you have any comments or questions about the NCKCN System, you can reach NCKCN by e-mail at: webmaster@nckcn.com

This page last updated 01/16/12 01:31:38 PM
©1996-2012 North Central Kansas Community Network