Day #121

Friday, September 22, 2000

The system now has water throughout and the crew is catching their breath and taking stock of what they have done.   Now, only tag ends remain, which is one of the most difficult stages of a large project and the least interesting.  Nonetheless, the work must be done to achieve total completion and James Haskins is making a list of those items.     

The city's contract with the state comes due October 1, 2000.   A short extension is being requested by the city to permit enough time to complete the project in a proper manner.


Table of Contents


If you have support or general questions please email us at: support@nckcn.com
If you have any comments or questions about the NCKCN System, you can reach NCKCN by e-mail at: webmaster@nckcn.com

This page last updated 01/16/12 01:32:28 PM
©1996-2012 North Central Kansas Community Network