Day #11

Thursday, April 13, 2000 

AM -- With no new leaks appearing over night, the team begins laying new pipe again today, going north from Patterson on Howe Street.  The plan is to lay both this block plus a service line to the only house on the block before nightfall, tying it off with the installation of a fire hydrant at the north end.  


PM -- Hydrant at north end of Howe.  Service line to home also installed. 

Focus tomorrow will turn to finishing Patterson to Omio, as well as linking the new line to the tower.  That will enable the city to pressure test the new line and then consider the abandonment of the old 8-inch line on Patterson that has caused so many problems over the years.    


Table of Contents

Next Day


If you have support or general questions please email us at: support@nckcn.com
If you have any comments or questions about the NCKCN System, you can reach NCKCN by e-mail at: webmaster@nckcn.com

This page last updated 01/16/12 01:31:17 PM
©1996-2012 North Central Kansas Community Network